PROJECT OVERVIEW

Square Footage

4,128 SF

Duration

3 months

Year Completed

2023

PROJECT DETAIL

For this tenant improvement TI Builders updated Schools First Federal Credit Union current downtown Sacramento office. All work for this project was completed during off-hours/ night work. This was due to the bank being fully operational during the day. Work consisted of upgrades to the entire space including the demolition of existing partitions, construction of new partitions, two new restrooms, a network room and other associated MEP improvements.

About

Schools First Credit Union

Schools First Federal Credit Union is a long time customer of TI Builders. We have successfully completed multiple projects with them and pride ourselves on our lasting positive relationship